Maintenance level: 1 (Scheduled Power Maintenance)
Scheduled Maintenance Report for HorizonIQ
Completed
The scheduled maintenance has been completed.
Posted Feb 29, 2024 - 14:35 CST
Update
This maintenance has been successfully completed. Thank you!

HorizonIQ Technical Support and Operations
Posted Feb 29, 2024 - 14:34 CST
Update
Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Feb 29, 2024 - 14:33 CST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 29, 2024 - 13:00 CST
Scheduled
Devices involved: CHI SAN Storage Array, Nimble, RP pure C, Rubrik backup device

Impact: No Downtime Expected

Event Duration: 2 hours

Description: HorizonIQ – Power maintenance Rack 15-16

Event: During this maintenance data center technicians will be performing replacement of dual APC Power units, side A and B, in rack 15-16 that contains SAN storage.

During the maintenance power connections will be moved to temporary power source while APC will be replaced and reprogramed, one side at the time.
Each power connection will see 2 disconnections, one to move to temporary power, and second with connection moving back to permanent APC.

You can stay updated throughout the window on our HorizonIQ Status website:

https://ot.horizoniq.com/

Thank You,
HorizonIQ Technical Support Department
Posted Feb 28, 2024 - 13:44 CST
This scheduled maintenance affected: Bare Metal and Dedicated Cloud Services (Chicago).