UPS Pre-Bypass Switch Test - Singapore (System-A)

Scheduled Maintenance Report for HorizonIQ

Completed

The scheduled maintenance has been completed.
Posted Jan 31, 2026 - 14:00 CST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 31, 2026 - 08:00 CST

Scheduled

This notice is to inform you of scheduled maintenance on UPS System A at our Singapore facility. During this window, the UPS will be placed in bypass mode to perform pre-bypass switch testing. Power redundancy will be temporarily reduced, but no customer impact is expected.
Posted Dec 01, 2025 - 22:36 CST
This scheduled maintenance affected: Bare Metal and Dedicated Cloud Services (Singapore).